Growth FAQ - Building
What inspections are required for a residence?
The typical inspections required for residential construction are listed below along with inspection codes and the phone numbers to call.
- Environmental Inspection (850-891-1800):
- First environmental (602): Inspection is made in conjunction with the first building inspection to ensure proper installation of sediment and erosion control barriers.
- Throughout the project sediment & erosion control barriers are monitored. (602)
- Final Inspection (604): Can be made with the final building inspection.
- Building Inspection (850-891-1800):
- Footing Inspection (100): Required when separate concrete footings are being poured. The inspection should be made after the trenches have been dug and reinforcing steel is in place, and prior to actually pouring the concrete.
- Slab Inspections (105): Required when a concrete slab or a monolithic slab/footing is to be poured. The inspection should be made after all formwork, termite treatment, vapor barriers, reinforcing steel and applicable rough plumbing inspections have been completed, but prior to pouring the concrete slab.
- Exterior Sheathing Inspections (106): To be made during or after the roof and wall sheathing is applied, and before covering with felt or siding.
- Framing Inspection (107): To be made after all the construction is dried in and after all applicable rough electrical, plumbing, mechanical and gas inspections have been made. There should be no insulation installed prior to the framing inspection.
- Insulation Inspection (109): To be made once the required insulation is installed. Blown in attic insulation will be inspected during the final inspection.
- Exterior Wall Covering Inspection (118): To be made once the required exterior siding or veneer and soffits are installed.
- Final Inspection (900): To be made after all work is complete. Electrical, plumbing, roofing, driveway, mechanical and gas inspections may be made prior to the final building inspection.
- Roofing Inspection (850-891-1800):
- New, Additions, and Reroofs for Townhouse or Duplex (917): The inspection is to be done, if possible, during the installation of the roofing, but in any case, prior to the final building inspection.
- ReRoof for Single Family - Detached only: A Nailing Inspection (115) is required, the spacing pattern should be 6" on center with 8-penny ring shank nails. The Secondary Barrier Inspection (116) is required, using an approved Type 226, type 1 or 2 felt, synthetic underlayment or for flat roofs, base sheet.
NOTE: The Nailing and Secondary Barrier Inspections MUST be inspected and approved prior to the installation of any Final roof covering (917). Once these have been approved the final covering may be installed and a final roof inspection scheduled.
- Electrical Inspection (850-891-1800):
- Temporary Pole (500): If electrical power from the house cannot be used and temporary construction power is required, the temporary service pole must be inspected prior to the service being connected.
- Rough-In Inspection (200): To be made after all electrical boxes and rough wiring is installed.
- Electrical Release (501): All breakers, circuits and receptacles have been installed and completed. Address must be on building.
- Final Inspection (901): To be made once power is connected to residence and all electrical work has been completed and all electrical trim is installed.
- Plumbing Inspection (850-891-1800):
- Rough-in Slab Inspection (401): To be made after all underground piping is in place and pressure test is applied, prior to covering of piping under slabs.
- Tub Set Inspection (403): To be made after all rough piping is installed, including tubs, and the system is filled with water or pressure test is applied.
- Sewer Inspection (400): If a new sewer connection is made, piping must be inspected prior to covering.
- Final Inspection (905): To be made after all plumbing work has been completed and all fixtures installed.
- Mechanical Inspection (850-891-1800):
- Rough-in Inspection (301): To be made after all rough ductwork is installed and after any required condensate lines and exhaust vents are installed.
- Final Inspection (903): To be made after all connections and appliance are installed and complete.
- Gas Inspection (850-891-7040):
- Rough-in Piping Inspection (300): To be made after all piping is in place and pressure test is applied.
- Gas Meter Set (502): To be requested with the Final Inspection. 24 hour notice for residential
- Final Inspection (902): To be made after all connections and appliance are installed and meter has been set.
- Certificate of Occupancy (C.O.) (850-891-7001 option 2):
After all inspections are finished a certificate of occupancy will be issued. A new house or addition cannot be occupied and permanent power cannot be provided without a certificate of occupancy. This is the final step.
Return to the FAQ Page